Housing retrofit · Pre-works air tightness testing

Pre-works air tightness testing for a social housing retrofit programme

For a social housing retrofit programme in the West Midlands, we carried out pre-works air tightness tests on a large batch of occupied homes, with certificates lodged and results sent to the client the same day.

A residential street of terraced houses in England
Photo: Mutney, via Wikimedia Commons (CC BY-SA 4.0). Illustrative photo, not homes from this programme.

At a glance

  • Pre-works air tightness tests on a large batch of occupied social homes for a PAS 2035 retrofit programme.
  • Tests were booked on the same day as the retrofit assessment wherever possible, so residents had one appointment.
  • Pulse testing suited occupied homes and let each tester cover far more homes a day.
  • Certificates were lodged the same day, with a daily list of completed homes sent to the client.
Work
Pre-works air tightness tests on occupied homes
Location
West Midlands
Client
Retrofit coordinator on a social housing decarbonisation scheme
Test method
Pulse low-pressure air tightness testing, PAS 2035 compliant

The brief

Under PAS 2035, homes in a retrofit scheme need an air tightness test before works, so the designers know how leaky each home is and the post-works test can prove the improvement. The programme covered a large number of social homes, mostly occupied, with retrofit assessments booked on the same days.

How we did it

  • Shared visits. We tested on the same day as the retrofit assessment wherever we could, so residents had one appointment instead of two.
  • Pulse testing. A Pulse air tightness test takes minutes and doesn't need a fan fitted in the front door, which suits occupied homes and lets one tester do far more homes a day.
  • Same-day certificates. Each test was lodged and the certificate filed in the client's tracker the same day, so the design team never waited for results.
  • Daily reporting. The client received a list of completed homes every evening.

The results

Results varied widely between homes of similar age and type, which is exactly why each home is tested rather than assumed. The design team could see which homes were already fairly airtight and which would benefit most from air sealing.

Questions about this kind of job

Why do retrofit homes need an air tightness test before works?
PAS 2035 requires air tightness testing before and after works, so the ventilation strategy can be designed safely and the improvement measured. The pre-works test is the baseline.
How many air tightness tests can you do in a day?
With Pulse testing and planned routes, one tester can usually test far more homes a day than with a traditional fan test. That is how we kept pace with a large programme without delaying the design team.
Do similar houses get similar air test results?
Not always. Homes of the same age and type can differ a lot depending on past works, windows, services and how they are lived in, which is why PAS 2035 tests each home.
Independent. We don't sell heat pumps.

Have an unusual building? We'll measure it.

Send us your drawings or book a site survey. Email us and we'll come back with a price.

Email info@oneheatloss.co.uk →

Or WhatsApp 07496 898392.